LIRNGroup
Send Inquiry
Case Studies/10 TPH Calcium Bentonite Kiln — Furnace Backfire & Stack Emissions
LIRN Solutions — Process Engineering

10 TPH Calcium Bentonite Kiln — Furnace Backfire & Stack Emissions

Investigation of recurring furnace backfire at a 10 TPH calcium bentonite processing kiln in Karnataka. Diagnostic found undersized ductwork causing inadequate draft and excessive inlet velocities.

Client and project details anonymized. Technical findings shared for reference only.

Key Results

85%
Fan draft recovered
74%
Energy saved
0
Backfire events after fix

--- title: 10 TPH Calcium Bentonite Kiln — Furnace Backfire & Stack Emissions category: Root Cause Analysis slug: kiln-bag-filter-rca description: Investigation of recurring furnace backfire at a 10 TPH calcium bentonite processing kiln in Karnataka. Diagnostic found undersized ductwork causing inadequate draft and excessive inlet velocities.

---

10 TPH Kiln — Furnace Backfire RCA

[Diagnostic Chart: Problem Timeline → Investigation → Root Cause → Solution → Results]

The Problem

Symptoms — 2–3 furnace backfires per week, 30–60 min downtime each. Visible stack emissions. Burner replaced twice without solving issue. Operating at 60% capacity due to unreliability.

Root Cause — Ductwork severely undersized. Two 600mm ducts consuming 85% of induced-draft fan capacity, causing system imbalance and poor combustion.

Technical Diagnosis

Gas Volume Calculation:

  • Feedstock: 2.5 m³/min
  • Combustion products: 3.5 m³/min
  • Moisture evaporation: 1.2 m³/min
  • Total: 432 m³/hr needed

Ductwork Problem:

  • Main duct: 400mm diameter (0.126 m² area)
  • Face velocity: 57 m/s (should be 15–20 m/s)
  • System pressure drop: 790 mm WC (fan rated for only 400 mm WC)
  • Result: Induced draft pulling air through furnace at excessive speed → incomplete combustion → carbon buildup → backfire

The Solution

1. Enlarge ducts from 400mm to 1000–1200mm (reduces velocity to 12 m/s) 2. Install cyclone before baghouse for coarse dust separation 3. Upgrade fan to rated capacity with soft-start 4. Optimize pulse cleaning — trigger at 120–130 mm WC differential pressure 5. Reduce ID fan speed post-fix: 47 Hz → 25–32 Hz = 74% energy savings

Results

Zero backfires in first 100 operating hours ✓ Stack emissions eliminated — 80% reduction visible ✓ Throughput recovered — 6 TPH → 9.8 TPH consistent ✓ Energy savings — 74% fan power reduction = ₹1,80,000/yr ✓ ROI — 8-month payback on ₹4,50,000 investment

---

Key Lesson: Equipment failures are often system design problems, not component failures. Burner didn't fail—the system was forcing it outside design parameters.